Construction in public spaces on 2nd floor, 1st floor

The coming weeks will bring construction in public areas of the building complex.

This work is being done, now, when building occupancy is relatively low, in order to complete the work before the arrival of new graduate students and the return of undergraduate students in the fall semester.

  • July 14-21
    Second floor of Shain inaccessible – installation of fire alarm system
    Shain occupants requiring access to Mathews / Daniels will have to cross on other floors (1,5,6)
  • July 22-29
    First
    floor of Shain inaccessible – installation of fire alarm system
    Shain entrance will be blocked
    All occupants must enter via Daniels Building, basement level, along Johnson Street (west entry)
  • July 27
    First floor of Mathews inaccessible – installation of fire sprinkler and fire alarm systems
  • Aug 25
    • Liquid nitrogen, gas cylinders, ect. will be accessible, but with significantly restricted hours
    • Shipping & Receiving will be maintained
    • Pedestrian traffic through corridor prohibited

Logistical arrangements will evolve during the course of the month-long construction period on first floor of Mathews. Please plan accordingly.

For the Facilities Committee – Bob McMahon, John Moore, Jeff Nielsen, Matt Sanders