The coming weeks will be a busy time for construction activities related to the new fire alarm system in the chemistry complex. Be aware that you may encounter construction crews working in various locations in …
Chemistry Building Project
Construction Update 10/12/2020
Tower Crane. Removal of the tower crane began Sunday with partial closing of University Avenue. The large movable crane that was used to erect the tower crane was installed in the closed lanes and its …
WiFi Network Upgrades
Preliminary Schedule – WiFi network upgrade Work beginning Fri Oct 9; approximately two days of work per floor floor 9 Daniels floor 1 Shain / Mathews floor B Shain / Mathews floor 8 Daniels floor 7 …
Construction Update 10/06/2020
The tower crane at the construction site will be dismantled from Sun Oct 11 through Oct 14. This activity will not directly impact the occupants of the chemistry complex, but it will affect pedestrian, bicycle, …
Construction Update 09/28/2020
Topping Out Ceremony. The Miron construction team topped out the new tower in August, hoisting a roof panel to the 10th floor with a small, ceremonial tree attached. Topping out means that the basic structure …
Construction in Mathews, Daniels stairwells – III
Construction in the Mathews and Daniels stairwells will resume next week. A construction crew will core holes in stairwell landings and install electrical components of the fire sprinkler system. Schedule Sept 29 – Oct 12 …
Construction Update 09/21/2020
New Tower. Last week we reported on the exterior of the new tower. Work continues there, as shown by the first photo, taken from across University Avenue at 7:40 AM on Saturday. Workers on a …
Storeroom Reopens
The storeroom will reopen today as planned. In addition, we’ve added some time slots in the morning, 8am – 10am. Please continue to make appointments on the google sheet. Also, the storeroom will be closed …
Construction Update 09/14/2020
New Tower. The exterior of the new tower is changing every day. More windows and decorative surfaces continue to be installed. On the east (Mills-Street) side of the tower, the yellow debris chute has been …
Magnetic Resonance Facility Service Interruptions
The fire sprinkler installation project is coming Oct. 5 – Nov. 13 to the second floor of the Matthews building, which will heavily impact the research capabilities of the Magnetic Resonance Facility. During this time, the second …