Skip to main content
University of Wisconsin–Madison
UW Crest
Department of Chemistry
College of Letters & Science
  • People Expand Collapse
    • All People
    • Faculty
    • Staff
    • Postdocs
    • Graduate Students
    • In Memoriam
  • Academics Expand Collapse
    • Graduate Degree Programs
    • Undergraduate
    • Courses
    • Syllabus Library
    • Academic Support
    • Student Organizations
    • Academic Calendar
    • Financial Support
    • Career Services
  • Research
  • Recognition & Awards
  • Seminars & Events
  • Facilities & Services Expand Collapse
    • Facilities
    • Building Info
  • Outreach Expand Collapse
    • Research Experience for Undergraduates (REU)
    • Wi Crystal Growing Competition
    • Middle School Science Bowl
  • Safety
  • About Expand Collapse
    • Welcome
    • Badger Chemist News
    • Fast Facts
    • Scholarships, Fellowships & Awards
    • Inclusive Excellence
    • Employment
    • Contact Us
  • Give
  • Home
  • Alumni & Friends
  • Community
  • Intranet
  • MyUW
  • Wellness
  1. Home
  2. Chemistry Building Project

Chemistry Building Project

Construction Update 12/16/2019

Posted on December 16, 2019

From a Year Ago…to Now It has been almost exactly a year since gross demolition began on the northern part of the Daniels wing: The old lecture rooms, some classrooms, parts of some labs, and …

Posted in Chemistry Building Project, Chemistry Building Project Weekly Updates

Construction Update 12/09/2019

Posted on December 9, 2019

New Tower. There is a lot happening in the new tower than cannot be seen from the loading dock or other locations in our existing building—and a lot that can be seen. Last week concrete …

Posted in Chemistry Building Project, Chemistry Building Project Weekly Updates

New Chemistry Tower Grows More Every Day

Posted on December 2, 2019

Construction workers install the second of two main trusses that will support the building above the larger lecture room and learning studio. [Photo by Prof. John Moore] By John Moore and Bob McMahon Project Leaders  …

Posted in Chemistry Building Project, News

Construction Update 11/06/2019

Posted on November 6, 2019

The driveway to the chemistry loading dock will be inaccessible on Thu Nov 7th and Mon Nov 11th. On Thursday, a concrete pump truck will be used to pour a portion of the floor slab …

Posted in Chemistry Building Project, Chemistry Building Project Weekly Updates

Construction Update 11/04/2019

Posted on November 4, 2019

New Tower. The loading dock was closed on Tuesday and Wednesday last week for backfilling of gravel around the sub-basement and basement walls. Unfortunately, weather has slowed installation of waterproofing and insulation on the upper …

Posted in Chemistry Building Project, Chemistry Building Project Weekly Updates

Construction Update 11/01/2019

Posted on November 1, 2019

The construction team needs to make a brief shutdown to the natural gas service to the Daniels wing – TODAY – Fri Nov 1st. The outage will commence at approximately 10:00 am and lasts approximately …

Posted in Chemistry Building Project, Chemistry Building Project Weekly Updates

Construction Update 10/28/2019

Posted on October 28, 2019

New Tower. The tower is now rising above ground level and preparations are being made for pouring concrete for the part of the second floor that will become the new information commons (library). Much shoring …

Posted in Chemistry Building Project, Chemistry Building Project Weekly Updates

Construction Update 10/23/2019

Posted on October 23, 2019

The driveway to the chemistry loading dock will be inaccessible on Tue Oct 29th and Wed Oct 30th. Construction crews will be using a conveyor system to back-fill around the foundation walls on the west …

Posted in Chemistry Building Project, Chemistry Building Project Weekly Updates

Construction Update 10/14/2019

Posted on October 14, 2019

New Tower. The big news last week was the largest concrete pour of the project—almost 11 hours long. Last Thursday, from 4 am to about 3 pm a concrete pump truck in the loading-dock area …

Posted in Chemistry Building Project, Chemistry Building Project Weekly Updates

Construction Update 10/07/2019

Posted on October 7, 2019

New Tower. The new tower area looks completely different from what you saw in the last newsletter. Shoring and concrete forms now cover much of the basement and first-floor areas in preparation for pouring concrete …

Posted in Chemistry Building Project, Chemistry Building Project Weekly Updates
  • Previous page
  • 1
  • 7
  • 8
  • You're on page 9
  • 10
  • 11
  • Next page

Contact Us

  • This field is for validation purposes and should be left unchanged.

Site footer content

University logo that links to main university website Part of the Universities of Wisconsin

Quick Links

  • Directory
  • Graduate Degree Programs
  • Undergraduate
  • Employment at Chemistry
  • Safety
  • Contact Us

Normal

  • Undergraduate Office
  • Graduate Office
  • Communications
  • Webmaster

Contact Us

  • 1101 University Avenue
    Madison, WI 53706
  • Map map marker
  • Email: connect@chem.wisc.edu
  • Phone: (608) 262-1486
    • facebook
    • x twitter
    • instagram
    • linkedin

Website feedback, questions or accessibility issues: connect@chem.wisc.edu | Learn more about accessibility at UW–Madison.

This site was built using the UW Theme Classic | Privacy Notice | © 2026 Board of Regents of the University of Wisconsin System.