New Tower. A lot has been accomplished in the excavation during the past two weeks. (There was no newsletter September 16, so this report covers two weeks.) Concrete was poured Thursday afternoon and evening in …
Chemistry Building Project
Construction Update 09/16/2019
Daniels Sub-basement. The new rooms in the Daniels sub-basement that will house a new emergency generator and other electrical equipment were finished some weeks ago. Last week workers were installing conduit ducts that will carry power …
Coming Soon — A New Chemistry Building
By John Moore and Bob McMahon, project leaders Earlier this year, the State Building Commission approved an increased budget of $133.1 million for the Chemistry Building Project, the project went out for bids, and construction is …
Notice 4/22/2019: Chemistry Loading Dock Inaccessible 4/25-4/28
The schedule of construction activities for this week has been revised: The loading dock will be inaccessible from 11:00 am – 5:00 pm on Thur Apr 25. The driveway and dock are needed for the …
Construction Notice 1/2/2019
The chemistry loading dock will be completely inaccessible on Thurs Jan 3rd because of the installation of the storm sewer for the new building. In the meantime, occupants of Shain Tower should not attempt to …
Construction begins on $133 million revamp of Chemistry Building
September 17, 2018 By Eric Hamilton (Originally published here.) By the time they graduate, more than half of the students at the University of Wisconsin–Madison will have taken a chemistry course, a demonstration of the central role …
State Building Commission Approves Revised Budget, Expanded Scope of Chemistry Building Project
On June 6, the State Building Commission approved a revised budget ($133.1 M) and authorized the solicitation of bids to construct the chemistry building project. This action will enable completion of the full scope of …
State Building Commission Grants Approval for Construction of Chemistry Building Project to Proceed
On Dec. 14, the State of Wisconsin Building Commission approved a key design report and granted the authority to construct the Chemistry Building Project. Following months of planning and design work, the university submitted for …
Chemistry Building Project Featured in Milwaukee Journal Sentinel
A story published Sept. 2 in the Milwaukee Journal Sentinel provides an updated look at the three chemistry-related building projects currently in process at UW-Madison, UW-Stevens Point, and UW-La Crosse. “UW-Madison will finally get its …
Chemistry Building Project Approved in State Capital Budget
When Governor Scott Walker signed the 2015-17 biennial budget on July 12, the final capital budget included $86.2 million in funding for the Chemistry Building Project. Despite initial signs that the project might not have been …