Heart-Lung Transplant Nearly Complete The Mathews wing continues to be closed to all occupants through April 30, so that the old exhaust system can be replaced with a new exhaust system that uses fans in …
Chemistry Building Project
Construction Update 04/19/2021
New Tower In addition to finishing the facades of the new tower, a lot more exterior work remains to be accomplished before we can move in. For example, sidewalks need to be completed, planters finished, …
Construction Update 04/12/2021
New Tower The exterior of the new tower looks better every day as workers apply terra cotta decorative panels to the north façade. The southwest and west façades are already finished, so it won’t be …
Construction Update 04/05/2021
Daniels Wing Rejuvenated after 16-Day Shutdown The Daniels wing re-opened right on time at 9:00 am, Wed Mar 31, at which time occupants returned, checked that fume hoods were working appropriately and restarted research work. …
Construction Update 03/29/2021
Daniels 16-Day Shutdown Nearly Complete Wow! The first half of the chemistry complex’s heart-lung transplant is nearly finished, and the patient is responding well to treatment. As this is written the Daniels wing remains closed …
Construction Update 03/22/2021
Daniels 16-Day Shutdown Continues on Schedule The Daniels wing of our building is closed to all occupants through March 30 to enable switchover to the new supply-air system. The reason for this long-overdue switchover is …
Construction Update 03/15/2021
Daniels 16-Day Shutdown Has Begun The Daniels wing of our building is closed to all occupants through March 30 to enable switchover to the new supply-air system. Occupants prepared their labs, offices, and other spaces …
Construction Update 03/08/2021
New Tower In preparation for the 16-day shutdown of Daniels that begins next Monday (March 15), a lot of work on infrastructure must be completed in mechanical areas on the ninth- and tenth-floors of the …
Construction Update 03/01/2021
New Tower Much of the infrastructure in the lower floors of the new tower is nearing completion, which allows for decorative finishes and artwork to be installed. For example, in the large lecture rooms, ceilings …
Construction 02/23/2021
New Tower A lot of work is going on inside the new tower in preparation for the 16-day shutdown of the Daniels wing that is scheduled for Marth 15 through March 30. During the shutdown, …