Chemistry Building Project Weekly Updates
Construction Update 1/7/2019
Gross demolition began Wednesday, December 19 on the part of the Daniels wing that housed the library and lecture rooms. Demolition has proceeded smoothly, beginning with the portico (where the bike racks used to be), …
Construction Update 1/2/2019
The chemistry loading dock will be completely inaccessible on Thurs Jan 3rd because of the installation of the storm sewer for the new building. In the meantime, occupants of Shain Tower should not attempt to …
Construction Update 12/17/2018
It is exciting to approach another milestone in progress toward our new facility. This week we are ready for gross demolition and almost ready to regain access to the old driveway to the loading dock. …
Construction Update 12/03/2018
A lot will be happening on our new building this week. The wall separating us from the demolition/construction zone will be completed, demolition of the north end of Daniels will begin, and access to the …
Construction Update 11/19/2018
Progress has been made on construction of the permanent concrete masonry wall that will separate the north end of Daniels from demolition and construction. The wall, which will be permanent, will be waterproofed and insulated. Once it …
Construction Update 11/12/2018
The heated restroom trailer outside the south exits from Daniels basement is now in operation. This clean, warm trailer is for UW-Madison students, staff, and faculty, to avoid crowding in the restrooms inside Daniels. It is …
Construction Update 11/5/2018
Last Thursday afternoon the large restrooms at the north end of the first floor of Daniels were closed off by construction barriers. Students in B, 1, and 2 of Daniels should be directed to the restroom …
Construction Update 10/29/2018
Today (Monday, October 29) occupants of Shain Tower are asked to be on a fire watch’: the fire sprinkler system will not be operable. Consider postponing any particularly hazardous procedures and be alert for fires. This …
Construction Update 10/22/2018
During the next couple of weeks, with very short notice of the exact date and time, we expect natural gas service to Daniels and Mathews wings to be shut off for up to half a day. If …