New Tower. Last week was incredibly productive. Concrete was poured for the west side of the seventh floor on Thursday. On Friday, the area of the sixth floor below the new pour was above 90 …
Day: March 2, 2020
Construction Update 02/24/2020
Mock-up. The mock-up in parking lot 45, across Mills Street from the power plant, was tested for water tightness last Tuesday and passed a slightly more stringent test than was required (12 psi versus 10 …